Project Description

 
KCC Mall de Zamboanga is touted to be the biggest mall in the Zamboanga peninsula with a total land area of 35,000 sq.meters and a total gross floor area of 120,000 sq.meters. The building houses a supermarket,department store,cinemas,retail shops, fast food stores and parking areas.

Scope of Works

 
Mechanical Works (Centralize Air Conditioning)

  • Ducting Works (Air Conditioning & Ventilating Ducts)
  • Chilled Water Piping System
  • Supply & Installation of Motor Control Center & Loose Controllers for all AHU’s & Blowers
  • Termination of electrical wiring’s for all MVAC Equipment’s (Load side only).

Automatic Fire Protection Sprinkler System

List of Equipment’s

  • 4 units of Water Cooled Chillers (3 units of 800 TR capacity & 1 unit of 400 TR)
  • 4 units of Cooling Tower with 1000 TR & 2400 GPM Capacity
  • 4 units of Chilled Water Pumps with 100 HP & 1920 GPM Capacity
  • 4 units of Condenser Water Pumps with 60 HP & 2400 GPM Capacity
  • 52+ units of Air Handling Unit
  • 5 units of Fan Coil Unit
  • 181 units of Fans & Blowers